Setup a Scheduler Job

In order for CM4D to generate events, you must setup a Scheduler Job with the appropriate settings. For more information on how to create Scheduler Jobs, see the CM4D Scheduler Manager Help Documentation.

1.     Open CM4D Scheduler Manager

2.     Set the following minimum parameters:

a.     Category - Static

b.     Enabled - Active

c.      Managed Documents - Double click to open the Managed Documents selection dialog. Check the box(es) next to the Managed Documents that you set up to run your Events with.

d.     Report Format - Event (this may also be set to Both)

e.     Type - DataProcessed

3.     If you want to use any other applicable job options, set those now.

4.     To apply your settings, click Save and then Exit.

5.     You are now ready to have generated Events sent through EventSmith.

Continue to the topic called Starting EventSmith to subscribe as an EventSmith User.